11 Irving Street Preconstruction/Design Development Proposal
Dear Christine,
Thank you for the opportunity to assist with the pre-construction phase of your upcoming home remodel. Our team is committed to delivering a seamless and well-organized experience from start to finish. This proposal outlines the key elements of the pre-construction process that we have discussed, including design coordination, cost estimation, timeline development, and any necessary permits or approvals. Our goal is to ensure that every detail is thoroughly planned, providing you with a clear roadmap for your project and minimizing any unforeseen challenges along the way. The estimate is based upon the scope of work below. We look forward to working closely with you to bring your vision to life.
Sincerely,
Nick Wise
Scope of Work
Carpentry
Furnish and install a new 24” vanity.
If floating we need to add blocking
Furnish and install a new vanity mirror
Furnish and install new baseboard
Furnish and install new bathroom door/trim - Folding Door
Plaster wall as needed
Plumbing
Furnish and install new toilet
Furnish and install new vanity faucet
Furnish and Install new tub
Furnish and install new shower valve, shower head, shower wand and drain
Electrical
Furnish and install a new bathroom fan.
Furnish and install new GFCI outlet to replace existing
Furnish and install an additional GFCI Outlet
Furnish and install radiant floor heating power/thermostat.
Furnish and install new vanity lighting.
Tile
Furnish and install tile wall with bullnose trim
Furnish and install a tile floor
Furnish and install radiant floor heating
Furnish and install tile threshold
Paint
Paint bathroom/trim
Demo
Demo Scope Items as needed
Remove debris and dispose
General Conditions
Supervision
Trash removal
Final clean
Off Hours Rough Inspection
Temp Protection
Final Clean
Material Selection List
Below are the material selections we previously discussed.
Please click on the items below for the link to the site
Carpentry
Vanity: With white quartz top, 3 Week Lead Time
Vanity Mirror: 1 Week Lead Time
Tile
Floor Tile: Ombre Color, 1 Week Lead Time
Wall Tile: Fantasy Beige Color, 1 Week Lead Time
Plumbing
Vanity Faucet: 2 Week Lead Time
Shower System: 2 Week Lead Time
Tub: 15 Day Lead Time
Paint
Need More Samples
Electrical
Ditra Floor Heat: 5 Day Lead Time
Wall Mounted Light: 1 Week Lead Time
Estimate
Demo
Demo all scope of work items and dispose
Total Demo Cost: $2,200
Carpentry
Furnish and install Bathroom Door, Frame, and Hardware (Materials included)
Install bathroom trim
Patch drywall as needed
Carpentry Labor: $1,200
Vanity (Material Allowance): $499
Bathroom trim (Material Allowance): $100
Vanity Mirror (Material Allowance): $250
Total Carpentry Cost: $2,049
Electrical
Furnish and install new Panasonic fan/light
Install new vanity light
Reuse GFCI circuit, upgrade breaker to be code compliant (AFCI)
Add second outlet location
Reuse all switch locations, replace with new
Reuse existing lighting circuit, upgrade breaker to be code compliant (AFCI)
Reuse existing toe kick heat circuit for floor heat circuit, upgrade breaker to be code compliant
AFCI/GFCI combo
Electrical Labor/Materials: $4,000Vanity light (Material Allowance): $150
Alternate Additions:
Replace existing GFCI circuit with a dedicated circuit ($300)
Replace toe kick heat circuit with dedicated ($300)
Total Electrical Cost: $4,150
Tile
Install new tile floor and shower walls above tub
Shower Tile: Chamonix Natural 30x60 Tile $7.39/SF (62 SF with 10% waste): $487
Floor Tile: Verona Cream 30x60 Tile $5.99/SF (19.8 SF with 10% waste): $126
Heated Floor (Schluter System): $750
Shower Niche with Bullnose Tile Trim: $120
Chamonix Natural Trim: $376
Misc. Materials: $100
Queen Beige Hon Threshold (91.5x11.5x2cm): $92
Total Tile Cost: $4,651
Plumbing
Plumbing Labor: $4,500
Toilet (Material Allowance): $300
Tub (Material Allowance): $712
Bathroom Faucet (Material Allowance): $150
Shower Valve Trim, Head, Tub Spout, Valve Kit (Material Allowance): $500
Total Plumbing Cost: $6,162
Painting
Paint Bathroom and Trim (Labor and Materials)
Total Painting Cost: $350
General Conditions
Supervision: $1,000
Protection: $650
Disposal: $500
Off-Hours Inspection for Rough Inspection: $250
Total General Conditions Cost: $2,400
Sub Total: $21,962.77
Permits: $300
Contingency (6%): $1,318
GC Fee & Profit (20%): $4,656
Total: $28,237
Schedule
Conclusion
We are excited about the opportunity to work with you and bring your project to life. Please note that the $250 pre-construction cost will be fully refunded and credited toward the final construction cost. Additionally, we understand that preferences may evolve during the construction process, and we are happy to accommodate any changes to the material selections through a change order. Our team is committed to ensuring a smooth and successful renovation, and we look forward to collaborating with you every step of the way.